How to Pour a Concrete Slab or Foundation Like a Pro Home Builder

To truly know your house from top to bottom, start with the foundation below

Suburban home with concrete driveway and green siding
Photo: hikesterson / iStock / Getty Images
Suburban home with concrete driveway and green siding
Photo: hikesterson / iStock / Getty Images
Nick P. Cellucci
Written by Nick P. Cellucci
Contributing Writer
Reviewed by Matt DiBara
Owner, DiBara Masonry
Updated October 28, 2022

Difficulty

Expert

Special skills and tools necessary—leave it to the pros.

Time to complete

24 hours

You must keep the concrete wet for two days if you use this DIY method. Hiring a pro to pour concrete is quicker and means less work for you.

Cost

$3,250+

Hiring a pro to pour a concrete slab costs $5 to $16 per square foot.

Need professional help with your project?
Get quotes from top-rated pros.

What you'll need:

TOOLS
  • Tape measure
  • Hammer
  • String
  • Level
  • Skid loader (optional)
  • Plate compactor
  • Metal-cutting blade
  • Bull float
  • Edging tool
  • Magnesium float
  • Steel trowel (optional)
  • Push broom (optional)
  • Garden sprayer
  • Safety glasses
  • Wood saw
  • Roller for waterproofing
SUPPLIES
  • Wooden stakes
  • Wooden kickers
  • Duplex nails
  • Forming lumber
  • 1/2-inch diameter rebar
  • 6-mil plastic sheeting
  • Concrete
  • Packable gravel fill
  • Tie wire
  • Foam insulation
  • Curing compound
  • Elastomer (for waterproofing)

Every great house starts with a strong foundation, and there are several essential steps to correctly pouring a concrete slab or foundation. It's crucial that you choose the right concrete, waterproof the foundation, and obtain the proper permits. Whether you build the foundation yourself or hire a contractor, it's wise to learn the ins and outs of the job so you can trust in your home's stability.

Prepping to Pour a Concrete Foundation or Slab 

Before learning how to pour a concrete foundation or slab, here are some tips to prevent mishaps.

Determine the Depth 

Before you dig a foundation, you'll have a piece of land and a vision of how you'd like your home to look. But before pulling up earth, determine how deep a foundation is required. On level ground with good soil conditions, 3 feet is a good estimate. For high-moisture soil or homes built on hillsides, you'll need more. Consult a local contractor or structural engineer to determine exactly how much.

Obtain Proper Permits

You or your contractor must obtain the proper local building permits, which will outline how close to the lot lines you’re allowed to build. Otherwise, your municipality could give you the bad news—long after pouring the foundation—that you need to make major changes to your house. Always obtain the proper paperwork. The cost of your permits should be factored in when determining the total cost to build your foundation (typically $4 to $25 per square foot).

Use the Correct Mix and Amount of Concrete

You and your contractor must do some homework before selecting the right concrete mix and determining the volume of concrete needed. Not enough water or too much in the mix can cause it to dry too quickly or not quickly enough, which could cause the foundation to settle and crack. Keep in mind that local humidity also affects the drying time.

High-strength concrete mix is the most popular choice for foundations, as it has exceptional durability. Your concrete company can recommend the best mix for your needs.

Wear Proper Protection

Wet concrete can irritate or even permanently damage your skin, so anyone working on this project should wear full-eye protection, long sleeves and pants, and rubber gloves. Consider tall rubber boots if you have to wade into wet concrete. If your clothes get saturated with cement, remove them immediately, thoroughly rinse your skin, and change into clean clothes.

Be Patient

As noted, your foundation is a critical component of your home’s construction. It may take two to six weeks to build and will likely be the most time-consuming part of your home build, but Rome wasn’t built in a day, right? Remember, your slab will still be soft for a day or two after curing is complete, so be patient and don’t build on top of it right away.

Now let’s get into the steps for pouring the concrete in more detail.

  1. Clear and Prepare the Site

    Start by clearing the site of any trees, shrubs, underbrush, stumps, large rocks, or pieces from any former construction. Position the slab site parallel to the lot line, then drive four stakes into the ground to roughly indicate the site’s corners.

    "Be extra careful to remove all the stumps and large roots. Over time, they will decompose and cause sinkholes if not carefully removed and properly filled in with new compacted material," says Matt DiBara, Angi Expert Review Board member and owner of DiBara Masonry.

  2. Set and Square the Frame

    Next, you’ll create forms for the foundation's footings, which are wooden frames used to hold the concrete in a particular shape when poured. Anywhere from 16- to 20-inch-wide footings are enough to handle the weight of a typical home. You may need larger footings and forms if you live on volatile ground or your home is expansive.

    Cut boards of forming lumber to the length of each side of the site and nail them to your wooden stakes. Brace the forms with additional vertical wooden stakes and kickers angled into the ground every 2 feet around the outside. Measure carefully to ensure that you set each board at 90 degrees from the ones it’s nailed to. Save the straightest boards for the top form so the edge is nice and straight.

  3. Fill and Level the Ground

    Using a line level and string or a builder’s level, measure down in multiple spots to see whether the site is sloped. Hire a professional excavator or use a skid loader to add or remove soil, build up low sides, or dig out high sides. Add a solid layer of gravel fill on top of your soil for the slab to sit on.

    Pack the fill down solidly using your plate compactor, sloping it down in a 12-inch deep by 12-inch wide trench along the perimeter so the edges of your slab will be thicker. Cover the fill with the plastic sheeting.

  4. Lay Rebar

    Depending on the slab’s thickness, you may need rebar to reinforce the concrete. With your fill in place, set metal stakes around the perimeter of your wooden forms, about 4 inches in. This will form a second perimeter for two rebar bands, strengthening your slab.

    Cut the rebar using a metal-cutting blade, bend it, and splice lengths together using tie wire until you’ve created two rebar perimeters set on top of each other. Next, lay a grid of rebar to partition the slab. Space the rebar 4 feet apart over the plastic sheeting, running the length and width of your site. Connect the intersections with tie wire.

  5. Pour the Concrete

    Workers leveling concrete foundation
    Photo: LivingImages / E+ / Getty Images

    Arrange to have concrete delivered on a day with a mild forecast. Avoid hot days, high winds, and rain. Check again to ensure that your forms are square, level, and well-braced, and have a few strong friends or contractors on-site to help with the pour. Concrete will be poured directly into your forms, which should keep it contained.

  6. Level and Round Off the Slab

    Drag a long, straight 2-by-4 screed board across the top of your forms to level the concrete, also known as screeding. It’s best to check your screed board using a string line to ensure it’s completely straight. Simply hold the spring line from end to end to verify. Make multiple passes until the concrete is flat. 

    Have one of your friends or contractors add or remove concrete in front of the screed board as needed as you pull it. Next, push a bull float across the screeded concrete to flatten it, keeping the leading edge slightly elevated. 

    Pull the float back across when you reach the far side of the form. Do this up to three or four times across the entire surface. Water may bleed out onto the surface, so wait for it to disappear and for the slab to harden slightly before rounding off the slab edges with an edging tool. Work the tool between the slab and the forms until all edges are smooth.

  7. Finish the Surface

    Wait until the concrete can support your weight to finish the surface. Kneeling on squares of foam insulation, use a magnesium float to smooth out bumps, dips, and pebbles left by edging and leveling. You may need to put some pressure on the float if your concrete starts to harden.

    To achieve a smooth finish, follow up hand floating by troweling with a steel trowel. For a rougher, nonslip finish, skip troweling and drag a push broom over the surface for a broom finish.

  8. Allow Concrete to Cure and Remove Forms

    Your concrete slab should take between three and 10 days to cure, during which time you’ll want to keep it moist. This will allow it to cure slowly and develop maximum strength. Spray your finished slab with a curing compound in a regular garden sprayer, following your product’s instructions on the label. Once the curing process is complete, you can carefully strip off the forms.

  9. Waterproof the Slab

    Finally, you can waterproof the slab by adding a sticky rubber substance called an elastomer.

    This substance retracts water so it can't seep into your walls or foundation and cause damage. Apply the elastomer with a roller or brush.

DIY Concrete Foundation vs. Hiring a Pro

Most homeowners should not pour a concrete foundation as a DIY project. The integrity of the entire home rests on the foundation, and improper installation can lead to serious problems with every part of the house. Even if you have the required specialized tools and experience, you will still need to spend thousands on the cost of having concrete delivered by a pro.

You may save on the cost of a small concrete slab for a patio with a DIY project, but those savings aren’t worth it for a home foundation. You’ll find trained foundation contractors near you with the right knowledge and equipment to properly excavate your property, evaluate your soil, pour your concrete, and leave you with an attractive finish.

Frequently Asked Questions

You should have at least 4 to 6 inches of compactable base under your concrete slab. Your contractor may recommend more depending on the structure.

Need professional help with your project?
Get quotes from top-rated pros.
Learn more about our contributors
Nick P. Cellucci
Written by Nick P. Cellucci
Contributing Writer
Nick has been a copywriter in the home services industry since 2017, marketing for hundreds of flooring and home improvement providers throughout North America.
Nick has been a copywriter in the home services industry since 2017, marketing for hundreds of flooring and home improvement providers throughout North America.
Reviewed by Matt DiBara
Owner, DiBara Masonry
Matt DiBara is the owner of Dibara Masonry in Los Angeles. He has worked on high-end and celebrity homes, and he’s also a licensed general contractor who’s well-versed in all areas of construction.
Matt DiBara is the owner of Dibara Masonry in Los Angeles. He has worked on high-end and celebrity homes, and he’s also a licensed general contractor who’s well-versed in all areas of construction.
The homeowners guide to Concrete Pouring and Repair
From average costs to expert advice, get all the answers you need to get your job done.