A new four (4)-lane toll road from Sto. Tomas, Batangas to Tayabas/Lucena City in Quezon, 66.74 km. long
The revised alignment is divided into six (6) packages as follows:
SECTIONS |
LENGTH (km) |
Package A: Santo Tomas, Batangas to Makban, Laguna |
11.32 |
Package B: Makban, Laguna to San Pablo, Laguna |
12.75 |
Package C: San Pablo, Laguna to Tiaong, Quezon |
7.50 |
Package D: Tiaong, Quezon to Candelaria, Quezon |
15.00 |
Package E: Candelaria, Quezon to Tayabas, Quezon |
10.21 |
Package F: Tayabas, Quezon to Brgy. Mayao, Lucena, Quezon* |
9.96 |
*Proposed TR4 Extension
This project aims to:
- Improve the transport of goods and services from Southern Provinces to Manila and vice versa.
- Shorten travel time, decongest, and reduce the volume of traffic plying the Pan Philippine Highway.
- Enhance the economic efficiency of the existing South Luzon Expressway (SLEX), allowing to meet the increasing demand of traffic volumes due to the rapid growth of population, urbanization, and economic development of Quezon Province and adjoining provinces.
At the end of construction, the project is expected to:
- Efficiently move people, products/goods and services to and from Laguna, Batangas, Quezon, and Bicol Region.
- Reduce travel time along the 58-kilometer stretch between Sto. Tomas and Lucena from 4 hours to 1 hour.
- Provide the motorists with safer and more convenient travel on modern tollway facilities like well-lit toll plazas, fiber optics, and CCTV cameras, among others.
SMC SLEX Inc. (formerly South Luzon Tollways Corporation)
Php 13.10 Billion (subject to adjustment due to additional section, Package F)
● Ongoing construction
Accomplishment based on IC’s Progress Report No. 102
Package TR4A: 20 %
Package TR4B: 39 %
Package TR4C: 63 %
Package TR4D: Not yet started
Package TR4E: 2 %
● On-going ROW acquisition by the DPWH
Unconditional PTEs/WOP
Package TR4A: 83.66 %
Package TR4B: 91.85 %
Package TR4C: 100 %
Package TR4D: 98.01 %
Package TR4E: 93.60 %
Total: 93.06 %
*TARGET DATE OF COMPLETION:
Package A : 2025
Package B : 2024
Package C : 2024
Package D : To be determined
Package E : 2024
Package F : Design Stage
*Target date of completion is based on Independent Consultant’s (IC’s) Progress Report