The Wayback Machine - https://web.archive.org/web/20071029030119/http://www.asce.org:80/pressroom/news/display_press.cfm?uid=2769
Membership Conferences Publications Continuing Education Join Renew MyProfile SiteMap Contact Help Logout Home
PANEL SAYS TUNNEL IS FEASIBLE FOR TYSONS CORNER


Media Contact(s):
Joan Buhrman
ASCE
(703) 295-6406
jbuhrman@asce.org

Scott Kasprowicz
Deputy Secretary of Transportation         
(804) 786-8032



July 31, 2006

PANEL SAYS TUNNEL IS FEASIBLE FOR TYSONS CORNER
Independent Panel of Engineers Confirms Feasibility, Cost Estimates and Schedule Impacts for Proposed Tunnel Portion of Metrorail Extension to Dulles International Airport

Reston, Va.—The American Society of Civil Engineers' (ASCE) Dulles Metrorail Tunnel Review Panel (TRP) today released the findings of their two month evaluation of engineering options for the Tysons Corner segment of the proposed Metrorail extension to Dulles International Airport. As a result of this technical review, the TRP stated that it would be feasible to construct the Metrorail system through the Tysons Corner area using a large bore tunnel, and that there was a relatively small difference in cost and schedule between the two options (large bore tunnel and largely aerial plan).

During a press conference releasing the report, Robert S. O'Neil, the TRP's chair, explained that Commonwealth of Virginia Secretary of Transportation Pierce Homer "did not ask our panel to recommend the preferred option. Instead, the Secretary asked our panel to ensure that the state had the best information available with which to make its decision. However... considering the magnitude and long-term impact of this project, and considering that the intangible benefits almost entirely favor the tunnel, it is reasonable to conclude that our findings suggest strong consideration of the tunnel alternative."

The TRP, which was formed by ASCE at the request of Secretary Homer, assessed the geology, tunnel alignment and physical limitations on the construction of the tunnel, as well as conducted a review of the project's estimates and proposals. In their report, the TRP stated that $2.5 billion would be a reasonable total cost to construct Phase 1 of the Dulles Metrorail Extension with a large bore tunnel through Tysons Corner. They also stated that after a similar review of the estimates for the largely aerial option, they believed the likely cost for the aerial alignment to be $2.25 billion.

In their review, the TRP noted that the expected duration of construction, installation and testing work for both alternatives would be comparable, but that the start of large bore tunnel solution would be delayed by up to one year to complete sufficient Preliminary Engineering and secure National Environmental Policy Act and equivalent State legislation approval. They also noted several cost saving features of the tunnel's lesser surface impacts, including a reduction in cost by at least $30 million for less permanent utility and temporary construction easements; and a savings of as much as $40 million due to lesser utility relocation and support costs. Other cost saving features of the tunnel option included: the large bore tunnel alternative allows for significant savings in operation and maintenance costs, an estimated $5 million per year (in current dollars); and, while they have not been calculated, life cycle cost savings would favor the tunnel. In addition, the TRP noted that optimizing competition, establishing financial incentives and risk-sharing in procurement actions would have high potential for eliminating excessive contingencies from pricing—yielding lower capital costs.

The aerial alternative, which the TRP noted would have half the expected life span of the tunnel (60 and 120 years, respectively), would also generate serious negative traffic and business access impacts during construction along routes 7 and 123, as well as Interstate 495, concurrent with the HOT Lane construction. While the large bore tunnel would have a much smaller impact in those areas, it would have substantial construction impact on median of Dulles Access Road, generating heavy truck traffic for the removal of tunnel muck created during boring, and for delivery and staging of pre-cast tunnel lining segments. The TRP concluded that despite being potential sources of project risk, the impacts would be manageable.

The TRP concluded that while it was clear that the aerial option could be done cheaper and faster, the large bore tunnel alternative would allow for a more integrated development of Tysons Corner. With more attractive development in place, and with greater development density allowed by the tunnel alternative, the TRP noted that it would be reasonable to assume that the tunnel option would provide a greater long-term economic and business impact than the aerial option.

The TRP's report is available for download on ASCE's Web site at: http://www.asce.org/files/pdf/TunnelReviewPanelReport.pdf.

ASCE is widely known for its infrastructure assessments and reports, including Building Performance Assessments of the World Trade Center, the Pentagon and the Murrah Federal Building, and its technical assessments following earthquakes, hurricanes and other natural disasters. Founded in 1852, ASCE represents more than 139,000 civil engineers worldwide and is America's oldest national engineering society.
-###-



   
Copyright © 1996 - 2007 | Comments | Privacy | Questions | Terms and Conditions | Webmaster