Silver Line Phase 2 Construction is Nearly 76 Percent Complete

Silver Line Phase 2 Construction at Reston Town Center (Photo via Capital Rail Constructors)Construction of Phase 2 of the Silver Line extension into Loudoun County is nearly 76 percent complete, according to a quarterly update by Capital Rail Constructors.

At a Wednesday meeting, the lead contractor on the project told the Metropolitan Washington Airports Authority that the project is on track. By 2020, officials hope to open the second phase of the line, which brings 23 miles of track past Dulles Airport and into Loudoun County.

Precasting work at the Reston Town Center Station will be completed by February. Mechanical, electrical and plumbing outfitting will continue through the fall of this year while roofing will finish by June.

Concrete work has been completed at the North Pavilion and precasting is almost finished. The breakdown of pedestrian bridges, provided by Capital Rail Constructors, is below:

Metal decking at the Herndon Station is complete as work on mechanics, roofing, skylights, elevators and the track continues. The concrete structure and utility work surrounding the South Pavilion has also been completed.

Most workers involved in the project โ€” 58 percent โ€” are from Virginia while 26 percent are from Maryland.

Photos via handout by Capital Rail Constructors

Recent Stories

The Fairfax County Board of Supervisors faces tough decisions ahead of next weekโ€™s budget markup session, following demands from local unions to increase county employeesโ€™ wages.Last week, dozens of countyโ€ฆ

Restonโ€™s popular community yard sale is temporarily moving down the road. More than 3,000 people are expected to attend the biannual event when it returns this Saturday (April 27), according to Reston Association, the organizer.

Morning Notes

Virginia bluebells bloom in Reston (photo by Marjorie Copson) Clifton Family Mourns Sons Killed in Fire โ€” โ€œWhen Fairfax County firefighters found two boys inside a fiery Virginia house earlierโ€ฆ

Marc Smith will serve as the new Herndon economic development director starting in May (courtesy Town of Herndon) The Town of Herndon is getting a new director of economic developmentโ€ฆ.

ร—

Subscribe to our mailing list